SR161 & I-270 Interchange
Description:
Total reconstruction and reconfiguration of the interchange of four-lane St. Rt. 161 with six-lane section of
Interstate 270 west of New Albany. The project also includes reconfiguration of the interchange with Sunbury Road.
It removes an existing bottleneck for west-bound commuter traffic and Port Columbus Airport traffic.
Corridor: For the corridor, it represented an important first step in overall corridor improvement.
Multi-Modal: It improved access to Port Columbus airport. It also relieved congestion on existing transit and van pool connections.
Status:
Next Step: The project is substantially complete and opened in November 2007.
Access Ohio: Macro Corridor
TRAC: $134 million in FY2004 dollars
Links: Project Web Site 161NExT.org
Updated: June 30, 2008